Hong Kong Airport – Second field trial on Deep Cement Mixing

Hong Kong Airport Authority completed the second field trial on Deep Cement Mixing (DCM) in January 2016.

The trial was to evaluate the performance of different contractors under various airport height restrictions and continuous operation, as well as collect valuable data, to optimise the construction planning and detailed design for the land formation of Hong Kong International Airport’s three-runway system.